IBM QRadar 7.5 Update Package 8 introduces one of the most significant upgrades in the QRadar 7.5 lifecycle by migrating the operating system from Red Hat Enterprise Linux 7 to Red Hat Enterprise Linux 8.
Although IBM provides official upgrade documentation, this guide focuses on the deployment process, prerequisite validation, and common issues encountered during production upgrades.
Last Verified
IBM QRadar 7.5 Update Package 8
Important
This guide supplements the official IBM documentation and should be used alongside the IBM release notes.
Prerequisites
Before beginning the upgrade, verify the following:
- QRadar 7.5 Update Package 7 Interim Fix 6 is installed.
- Current configuration and data backups exist.
- A maintenance window has been scheduled.
- Console or hypervisor access is available.
- The Update Package 8 SFS image has been downloaded from IBM Fix Central.
- Physical or virtual console access is available if GRUB authentication has been configured.
Verify the Required Kernel
Update Package 8 requires the kernel included with QRadar 7.5 Update Package 7 Interim Fix 6. Systems running an earlier kernel will not successfully complete the migration to RHEL 8.
Verify the installed kernel packages.
rpm -qa | grep kernel
Verify the running kernel on every appliance.
/opt/qradar/support/all_servers.sh "uname -a"
Important
The running kernel must report 105 before proceeding with the upgrade.
Temporarily Remove GRUB Authentication
Many STIG-hardened deployments require authentication at the GRUB menu before the operating system can boot.
Because the Update Package 8 installer performs multiple reboots, temporarily removing GRUB authentication can eliminate unnecessary trips to the console during the upgrade.
Navigate to the GRUB configuration directory.
cd /boot/efi/EFI/redhat
Back up the current configuration.
cp user.cfg /home/stiguser/
Remove the active configuration.
rm user.cfg
Rebuild the GRUB configuration.
grub2-mkconfig -o /boot/efi/EFI/redhat/grub.cfg
Reboot the appliance.
reboot
Verify the appliance boots normally without prompting for GRUB authentication.
Field Note
During one upgrade, a server remained on a black screen after rebooting. The system required a hard power cycle through the management controller before the boot process continued.
Upgrade Procedure
IBM provides complete release notes for Update Package 8.
https://www.ibm.com/support/pages/node/7032144
The following summarizes the deployment process.
Create the Updates Directory
mkdir -p /media/updates
Copy the Update Package
Copy the Update Package 8 SFS image to:
/storetmp
Mount the Update
cd /storetmp
mount -o loop -t squashfs \
750-QRADAR-QRSIEM-2021.6.8.20240302192142.sfs \
/media/updates
Run the LEAPP Precheck
Before beginning the operating system migration, execute the LEAPP validation.
/media/updates/installer --leapp-only
Resolve all reported issues before continuing.
Install Update Package 8
/media/updates/installer
When prompted, select:
all
Allow the installer to complete all upgrade stages.
Clean Up
Unmount the installation media.
umount /media/updates
After the upgrade completes:
- Clear the browser cache.
- Remove the SFS image from every appliance.
Troubleshooting
LEAPP Reports Patch-Sensitive Files
During testing, several appliances failed the LEAPP validation with an error similar to:
Cliniq has detected unresolved patch-sensitive issues.
You must resolve these issues before continuing.
Remediation:
Remove the dump files to avoid issues during the upgrade.
The reported files were located in:
/store/jheap
Specifically:
ccpp-*
Delete only the directories identified by the installer.
After cleanup, rerun the installer.
/media/updates/installer
Field Note
Do not remove every file from
/store/jheap. Delete only the files or directories specifically identified by the LEAPP validation.
LEAPP Fails Because Root Login Is Disabled
On STIG-hardened deployments, the LEAPP validation may fail if direct root SSH login has been disabled.
Edit the SSH configuration.
vi /etc/ssh/sshd_config
Change:
PermitRootLogin no
to:
PermitRootLogin yes
Restart the SSH service.
systemctl restart sshd
Run the LEAPP validation again.
/media/updates/installer --leapp-only
Warning
Restore the original SSH configuration after the upgrade has completed to maintain compliance with your organization’s security requirements.
Verification
After the upgrade completes, verify the following:
- Every appliance upgraded successfully.
- The QRadar Console is accessible.
- Managed Hosts reconnect successfully.
- Deploy Changes completes without errors.
- Event collection resumes.
- Flow collection resumes.
- Installed applications start successfully.
- High Availability status is healthy, if applicable.
- Browser cache has been cleared.
- Temporary installation media has been removed.
Verify the operating system version.
cat /etc/redhat-release
Verify the running kernel.
uname -r
Verify all managed hosts are online.
/opt/qradar/support/all_servers.sh "hostname"
Additional Resources
- IBM QRadar Update Package 8 Release Notes
- IBM Fix Central
- IBM QRadar Upgrade Documentation